Common

  • data1 upgrade complete
    • Switch from RAID-0 to RAID-10 for reliability.
    • Upgrade to Ubuntu 10.04 LTS
    • Upgrade to Postgres 8.4 and install PostGIS for eventual GIS work (probably move geometry here).
      • Planned upgrade to Postgres 9 once it becomes available.
    • Upgrade to MySQL 5.1
  • New production web server
    • It's fast.
  • Eventually will get failover working (but it spontaneously reboots the old server?!)
  • The old production web server is operating as a backup right now.

  • Process questions
    • Wrong answer coded in somehow for #8, #12 (Cosmic/CMS)

  • You must answer questions despite what the instructions say!
    • Talk on the design of the test in general?

CMS

  • Rundata should be exposed on the production system
  • Design specs needed for the events?
    • 2000 events authorized
    • Create punch list, GANTT chart, etc?
    • Tell TomM on the tasks he need to do?
  • EVO meeting?

LIGO

  • Issues with the (content) test questions
  • Question 4 in CMS/Cosmic process is missing from LIGO
  • Text problems that needs to be resolved (except question 15 - major issues)
    • Answers are correct
  • Do we remove the LOs in the LIGO test?

  • Not really training teachers to use the eLab in a way to handle the DRK12 test regime?
  • Focus more on the LOs - bring teachers into the context?
  • Need to be discussed in a future TC (and with jean?)

-- Main.PhongNguyen - 22 Dec 2010
Topic revision: r35 - 2010-12-22, PhongNguyen
This site is powered by FoswikiCopyright © by the contributing authors. All material on this collaboration platform is the property of the contributing authors.
Ideas, requests, problems regarding Foswiki? Send feedback