Meeting Notes for 11 March 2009 
Present: Liz, Marge, Eric, Bob, TomJ, TomL, Phong 
Absent: Mihael
  Action Items 
 
-  Someone needs to tell Marge what to tell the reviewers next Monday
 
 
  UI Peer Review/Feedback Test Next Week 
 
-  Jeanne, Jenny, Dale, Nate
  -  This cannot be delayed any longer
  -  Teacher updates first, student pages second
  -  List what can be tested / not-tested 
-  New execution mode decision has to be made ASAP 
-  Bob has signed off on UI
  -  Fine to be tested for peer-review, even if it's nonfunctional (UI is paramount in this test)
 
 
 
 
  -  Put in 
TRUNK code on www12 or www17 for this testing so we can display new features? 
  -  Have a reviewer act as a teacher, register students, then log in as a student and go through the process flow. 
 
 
  Future Peer Reviews 
 
-  Do small incremental tests
  -  Do big test upon a major release. 
 
 
  Cosmic 
 
-  Pre/post-test nearly done - Phong is attempting to break his implementation
  -  Teacher Pages → Classroom notes could be moved to the wiki, add link to the community 
-  Marge wants one link to go to somewhere in the forum or library (and the target page must look like a normal teacher page) 
 
 
  -  TomJ and Bob will be going to SEA next week to work on blessing issues 
  -  Bob is concerned about lots of small random issues appearing on Production.  
-  Bob says it was working better and more stable last Summer - how can we get back to that? 
 
 
 
 
  LIGO 
 
-  Task 2.3.7 has a lot of work done on it
  -  Task 2.3.9 is done (Bluestone-on-ANL) 
 
 
  CMS 
-- Main.PhongNguyen - 11 Mar 2009